Eagle Custom Homes Ltd

City of Winnipeg

Building permit history · CanPermits

Also filed on permits as “Eagle Custom Homes”

Total Permits
44
Total Project Value
First Permit
2014-04-29
Last Permit
2019-11-05

Compiled record

Export (Excel)

Declared construction value

Declared public-record values stated on the permits — not estimates, appraisals, or a quality signal.

Not enough permits carry a declared value to summarize (0 of 44 on record).

Project type

The kinds of permits this contractor pulls, by the project type recorded in the source permit.

Housing 44

Activity by year (permits per year)

1
'14
2
'15
12
'16
15
'17
10
'18
4
'19

Compiled from City of Winnipeg building-permit records (first-party permit record). CanPermits surfaces public permit records only and does not verify identity, licensing, or other business credentials.

This record covers building permits the City of Winnipeg publishes openly. Many jobs need no permit at all — so a real track record is almost always larger than what appears here. Absence of records is not absence of activity.

See an error in this record?

Work distribution

44 permits on public record
Loading map…

Work type

Construct New 40
Develop Lower Level 2
Partial Permit-Foundation 2

Building type

SFD & Att. Gar. 42
Duplex / Side by Side 1
SFD 1

Permits

Showing 44 of 44 permits.

Date ↓ Address Work type Value
2019-11-05 124 Tackaberry WAY Construct New
2019-10-17 124 Tackaberry WAY Partial Permit-Foundation
2019-01-31 166 Daylan Marshall GATE Construct New
2019-01-16 50 Shady Shores DR W Develop Lower Level
2018-10-19 12 Thelon WAY Construct New
2018-08-09 149 Daylan Marshall GATE Construct New
2018-07-10 66 Daylan Marshall GATE Construct New
2018-07-10 107 Tascona RD Construct New
2018-05-28 43 Crimson WAY Construct New
2018-05-01 42 Thelon WAY Construct New
2018-03-19 206 Daylan Marshall GATE Construct New
2018-03-02 121 Daylan Marshall GATE Construct New
2018-02-06 90 Tackaberry WAY Construct New
2018-01-19 186 Daylan Marshall GATE Construct New
2017-10-25 151 & 151A Tennant GATE Construct New
2017-10-19 151 & 151A Tennant GATE Partial Permit-Foundation
2017-07-27 141 Tackaberry WAY Construct New
2017-07-11 78 Tackaberry WAY Construct New
2017-07-11 37 Bow Water DR Construct New
2017-07-11 194 Tennant GATE Construct New
2017-07-11 198 Tennant GATE Construct New
2017-07-11 81 Tackaberry WAY Construct New
2017-05-25 78 Park Springs BAY Construct New
2017-05-25 42 Tackaberry WAY Construct New
2017-04-27 20 Tennant GATE Construct New
2017-03-21 121 Tackaberry WAY Construct New
2017-02-28 60 Bow Water DR Construct New
2017-02-07 47 Bonaventure DR W Construct New
2017-01-20 218 Tennant GATE Construct New
2016-12-22 49 Bonaventure DR E Construct New
2016-12-09 53 Tackaberry WAY Construct New
2016-08-31 244 Bonaventure DR E Construct New
2016-08-31 39 Larry Vickar DR E Construct New
2016-07-19 5 Bonaventure DR E Construct New
2016-07-19 108 Bonaventure DR E Construct New
2016-05-12 31 Larry Vickar DR E Construct New
2016-04-19 192 Bonaventure DR E Construct New
2016-03-31 204 Bonaventure DR E Construct New
2016-03-11 150 Water Ridge PATH Construct New
2016-03-04 88 Bonaventure DR E Construct New
2016-03-04 35 Heronswood PATH Develop Lower Level
2015-06-16 303 Bitterfield DR Construct New
2015-04-27 35 Heronswood PATH Construct New
2014-04-29 150 Kaur Umber TRAIL Construct New

Eagle Custom Homes Ltd: ≥44 permits on public record in City of Winnipeg · earliest permit on record 2014 · most recent 2019. Compiled from municipal building-permit records; CanPermits does not verify licensing or business credentials.