Addition permit

71 FRONT ST W

Toronto , Ontario

Issued
Issued Mar 13, 2020
Project type
Addition
Value
$8.0M
Status
Completed

Activity at this address

151 permits since 2008

Most recent activity: Jun 2026

Institutional

This permit is one of 151 permits filed at this address.

21 14 7 0 2019 2020 2021 2022 2023 2024 2025 2026
See everything happening at this address · 151 permits
Permit No. 20 113637 BLD Currently completed

Revision history

4 revisions on file · 2020–2022

  1. Closed Rev 03 Issued Oct 13, 2022
    Revision 03 - revised to include width of staircase at 71 Front St. W., the addition of a new detail to close the gap between the stair and the exterior wall, and the addition of a new plexiglass end … Read full revision note

    Revision 03 - revised to include width of staircase at 71 Front St. W., the addition of a new detail to close the gap between the stair and the exterior wall, and the addition of a new plexiglass end plate between the handrail and exterior wall at platform level to close off the gaps.

  2. Closed Rev 02 Issued Feb 25, 2022
    Revision 02 - revision to relocate sump pit from original location to a new location under staircase This reduces the likelihood of damage to electrical equipment by relocating the sump pitfrom its' o… Read full revision note

    Revision 02 - revision to relocate sump pit from original location to a new location under staircase This reduces the likelihood of damage to electrical equipment by relocating the sump pitfrom its' original location in the vestibule of the electrical room (shown on City-stamped permit drawings) to its own dedicated room and re-routing the associated pumped sanitary line

  3. Closed Rev 01 Issued Aug 05, 2021
    Revision 01 - Project entails converting 3 heritage freight elevators into additional stairs serving Platform 20/21. Other mechanical and electrical upgrades along the platform and within the concours… Read full revision note

    Revision 01 - Project entails converting 3 heritage freight elevators into additional stairs serving Platform 20/21. Other mechanical and electrical upgrades along the platform and within the concourses and teamways included to facilitate the upgrades. Refer to drawings previously approved for Building Permit 20 113637 BLD 00 BA. The revised drawings of this re-submission include: deferral of heritage scope and elevator enclosure re-supporting works; optimizing foundations to reduce number of helical piles and avoid relocating existing Tw sump pit, electrical plant and elevator equipment; modifications to architectural finishes including handrail & glazing; and, optimizing PA & CCTV device placement & utilizing platform hub cabinets to reduce quantity of speakers, cameras, cabling and riser reconstruction. Note that the Mw West Power Room (R-W602A) Mechanical, Electrical and Plumbing services is being designed as part of Metrolinx Project No 189503 and will be subsequently prepared and submitted as a revision to this permit.Proposal for interior alterations to the transportation hub of union go station. work consist of 3 freight elevators into additional stairs serving platforms 20/21. also associated mechanical and plumbing to support renovation.

  4. Closed Rev 00 Issued Mar 13, 2020
    Proposal for interior alterations to the transportation hub of union go station. work consist of 3 freight elevators into additional stairs serving platforms 20/21. also associated mechanical and plum… Read full revision note

    Proposal for interior alterations to the transportation hub of union go station. work consist of 3 freight elevators into additional stairs serving platforms 20/21. also associated mechanical and plumbing to support renovation.

Every revision the municipality has published for this permit, read directly off the source record rather than the single collapsed status most permit trackers show.

Issued / completed Application / inspection Cancelled / refused

Permit details

The municipal record for this permit.

Issue date
Mar 13, 2020
Project value
$8.0M
Project type
Addition
Building type
Commercial category
Institutional
Description
Proposal for interior alterations to the transportation hub of union go station. work consist of 3 freight elevators into additional stairs serving platforms 20/21. also associated mechanical and plumbing to support renovation.
Builder name
Permit status
Completed City's exact wording: Closed
Work type
Building Additions/Alterations
Completed
2023-10-26
References & corrections IDs · source · attribution
Permit ID 20 113637 BLD
Full address Front Street West, Toronto, Ontario, M5E 1X8, Toronto, M5E 1X8
Page URL

Contains information licensed under the Open Government Licence, City of Toronto.

Nearby active addresses

Other addresses with recent permit activity near this permit.