New Build permit
76 ADELAIDE ST W
Toronto , Ontario
- Issued
- Issued Nov 13, 2018
- Project type
- New Build
- Value
- $1.8M
- Status
- Completed
Activity at this address
120 permits since 1990
Most recent activity: Feb 2024
This permit is one of 120 permits filed at this address.
Revision history
2 revisions on file · 2018–2021
-
Closed Rev 01 Issued Jan 12, 2021
Telecom and office area 1. Replacing single wall diesel fuel storage tank with new double wall tanks (Basement level)2. Spraying the ceiling with 2 hour fire resistant material 3. Some walls will be p… Read full revision note Show less
Telecom and office area 1. Replacing single wall diesel fuel storage tank with new double wall tanks (Basement level)2. Spraying the ceiling with 2 hour fire resistant material 3. Some walls will be partially removed to facilitate the tanks constructions. Walls will be reconstructed once tha tanks are in place.
-
Closed Rev 00 Issued Nov 13, 2018
Telecom and office area 1. Replacing single wall diesel fuel storage tank with new double wall tanks (Basement level)2. Spraying the ceiling with 2 hour fire resistant material 3. Some walls will be p… Read full revision note Show less
Telecom and office area 1. Replacing single wall diesel fuel storage tank with new double wall tanks (Basement level)2. Spraying the ceiling with 2 hour fire resistant material 3. Some walls will be partially removed to facilitate the tanks constructions. Walls will be reconstructed once tha tanks are in place.
Every revision the municipality has published for this permit, read directly off the source record rather than the single collapsed status most permit trackers show.
Permit details
The municipal record for this permit.
- Issue date
- Nov 13, 2018
- Project value
- $1.8M
- Project type
- New Build
- Building type
- Commercial
- Commercial category
- Office
- Description
- Telecom and office area 1. Replacing single wall diesel fuel storage tank with new double wall tanks (Basement level)2. Spraying the ceiling with 2 hour fire resistant material 3. Some walls will be partially removed to facilitate the tanks constructions. Walls will be reconstructed once tha tanks are in place.
- Builder name
- —
- Permit status
- Completed City's exact wording: Closed
- Work type
- Building Additions/Alterations
- Completed
- 2024-04-29
References & corrections IDs · source · attribution
Contains information licensed under the Open Government Licence, City of Toronto.