Permit No. 09 195968 BLD Currently completed

Revision history

4 revisions on file · 2011–2012

  1. Closed Rev 01 Issued Aug 07, 2012
    cREVISION #1 to construct a temporary partial height drywall partion wall in room stores 1 -DK-7. Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (T… Read full revision note

    cREVISION #1 to construct a temporary partial height drywall partion wall in room stores 1 -DK-7. Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting facilities (maintenance plant and food & laundry bldg).

  2. Closed Rev 02 Issued May 16, 2012
    REVISION #2 INSTALLATION OF A PRE ACTION SUPRESSION SYSTEM, FIRE ALARM VERIFICATION Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and suppo… Read full revision note

    REVISION #2 INSTALLATION OF A PRE ACTION SUPRESSION SYSTEM, FIRE ALARM VERIFICATION Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting facilities (maintenance plant and food & laundry bldg).

  3. Closed Rev 03 Issued Jan 18, 2012
    Revision 03: To remove fire resistance rating of security wall in tower "A". (Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting … Read full revision note

    Revision 03: To remove fire resistance rating of security wall in tower "A". (Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting facilities (maintenance plant and food & laundry bldg).

  4. Closed Rev 00 Issued Feb 25, 2011

    Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting facilities (maintenance plant and food & laundry bldg).

Every revision the municipality has published for this permit, read directly off the source record rather than the single collapsed status most permit trackers show.

Issued / completed Application / inspection Cancelled / refused

Permit details

The municipal record for this permit.

Issue date
Jan 18, 2012
Project value
Project type
New Build
Building type
Description
Revision 03: To remove fire resistance rating of security wall in tower "A". (Proposed construction of the new Toronto South Detention Centre (TSDC), Toronto Intermittent Centre (TIC), and supporting facilities (maintenance plant and food & laundry bldg).
Builder name
Permit status
Completed City's exact wording: Closed
Work type
New Building
Completed
2012-08-22
References & corrections IDs · source · attribution
Permit ID 09 195968 BLD
Full address Horner Avenue, Toronto, Ontario, M8W 2B3, Toronto, M8W 2B3
Page URL

Contains information licensed under the Open Government Licence, City of Toronto.

Nearby active addresses

Other addresses with recent permit activity near this permit.