Renovation permit
580 COMMISSIONERS ST
Toronto , Ontario
- Issued
- Issued May 04, 2026
- Project type
- Renovation
- Status
- Issued
Activity at this address
45 permits since 2004
Most recent activity: May 2026
This permit is one of 45 permits filed at this address.
Revision history
3 revisions on file · 2025–2026
-
Revision issued Rev 01 Issued May 04, 2026
Rev 01: The original design proposed replacing the existing gas-fired MAU and heating units. To align with the City’s zero-emission requirement, the design has been revised to electric MAU and unit he… Read full revision note Show less
Rev 01: The original design proposed replacing the existing gas-fired MAU and heating units. To align with the City’s zero-emission requirement, the design has been revised to electric MAU and unit heaters.Convert paint spray room to repair area to install a wheel allignment machine and a wheeltrans bus lift (TTC)
-
Application received Rev 01 Applied Mar 27, 2026
Rev 01: The original design proposed replacing the existing gas-fired MAU and heating units. To align with the City’s zero-emission requirement, the design has been revised to electric MAU and unit he… Read full revision note Show less
Rev 01: The original design proposed replacing the existing gas-fired MAU and heating units. To align with the City’s zero-emission requirement, the design has been revised to electric MAU and unit heaters.Convert paint spray room to repair area to install a wheel allignment machine and a wheeltrans bus lift (TTC)
-
Permit issued Rev 00 Issued Jun 03, 2025
Convert paint spray room to repair area to install a wheel allignment machine and a wheeltrans bus lift (TTC)
Every revision the municipality has published for this permit, read directly off the source record rather than the single collapsed status most permit trackers show.
Permit details
The municipal record for this permit.
- Issue date
- May 04, 2026
- Project value
- —
- Project type
- Renovation
- Building type
- —
- Commercial category
- Institutional
- Description
- Rev 01: The original design proposed replacing the existing gas-fired MAU and heating units. To align with the City’s zero-emission requirement, the design has been revised to electric MAU and unit heaters.Convert paint spray room to repair area to install a wheel allignment machine and a wheeltrans bus lift (TTC)
- Permit status
- Issued City's exact wording: Revision Issued
- Work type
- Building Additions/Alterations
References & corrections IDs · source · attribution
Contains information licensed under the Open Government Licence, City of Toronto.
CanPermits is not perfect.
Please correct us.
Nearby active addresses
Other addresses with recent permit activity near this permit.